Playground at McKenzie Splash Pad to Open in Spring

By Brad Sam, brad@mckenziebanner.com
From the Feb 3, 2026 e-Edition
Photo by Brad Sam/The Banner
New playground equipment is in place next to McKenzie's splash pad. Installation will be complete by spring.

Area kids will have even more to do in downtown McKenzie this spring as a new playground is being installed adjacent to the McKenzie Station Splash Pad between Waldren Street and North Stonewall.

According to Parks Director Billy Hollowell, the equipment is in place. Between now and spring, the ground will be leveled, concrete poured and soft surfacing applied.

The new facility will open in conjunction with the splash pad opening for the season, typically in May.

Features of the new playground include two slides, a climbing wall and an elevated fort and tunnel.

The playground is geared toward ages 2-12.

The equipment was acquired last year when a favorable price could be secured. The work is being performed by the Parks and Recreation Department, further reducing the total price of the project.

Appearing in last year's budget, the total cost of the new playground is $32,000, funded fully by the city.

Advertisement
Print Issue: 2-3-26
McKenzie Banner February 3, 2026

In the e-Edition

McKenzie Banner February 3, 2026

Feb 3, 2026 · Read the full issue →

Related Stories

© Copyright 2026 Tri-County Publishing, Inc. | Privacy | Terms
Powered by Novel.ad